The working platform for drilling work is called drilling rig. It holds the
most components required for the drilling work. Main components comprise the
drilling rig are:
1. Power system, 2. Hoisting system 3.
Rotary system 4. Circulating system
5. Well control & monitoring system
Power system basically provides all of the necessary power to carry out the
drilling work. Normally this power is generated from local combustion
generators. A common drilling rig requires approximately 1000-3000 horse power
to maintain the operation. However, the power efficiency can be varied from
place to place. Generally, the mechanical efficiency of the generator is
favorable to work in low altitude and medium temperature environment.
Hoisting system is one of the main parts to actually doing the drilling job.
Either drill pipe or casing will be lifted and lowered to drill and complete the
well. It mainly composes of the derrick, tackle & block system and dead
line anchor system. Tackles and block do the vertical movement to the pipe.
People working on the derrick can help to safely place these pipes in the right
position. The dead line anchor mainly helps the replacement of the drilling
line when it was subjected to wearing.
Wells are drilled by the pipe & bit rotation, therefore it is very
important to have an efficient rotation system. This system mainly includes
swivel, Kelly, rotary drive and rotary table. The working principle of rotation
system is the Kelly, which is connected to the drill pipe drove by the rotary
table and then the whole drilling string can be rotated for drilling.
In order to keep the drilling operation without issues, proper circulation
system should be built to fulfill the requirement. Working scenario of
circulating system is the drilling mud will be pumped into the drill pipe from
the mud reservoir, we called it mud pit. After mud reached the bottom of the well,
it brings rock cuttings to the surface through the annulus between drill pipe
and well wall. The mud with rock cuttings will be separated through surface
solid control system, such as screens, de-sanders or centrifuges. After these,
clean drilling mud will be retreated with certain chemicals and again pumped
into the wellbore.
Drilling a well is very dangerous because the pressure in the reservoir
could be significantly high, which normally is about a couple thousand psi.
Therefore, in order to guarantee the drilling operation is safe and prevent an
undesirable accident, a well control system must be installed. The main part of
this system is the blowout preventer. This equipment is set on the top of the
well bore. If there is a sudden pressure change in the well which push the
formation fluid up to the surface, BOP will be closed the seal the well from
blowout. The course material is based entirely on the U.S. Army Corps of
Engineers' Engineering Manual EM 1110-1-1804: Drill Rig and Appurtenant
Equipment.
At the
conclusion of this course, the learner will have a better understanding about
the Drill Rig and Appurtenant Equipment as well as the following: